Anais dos Seminário de Energia, Utilidades e Gases Industriais


ISSN 2594-3626

Título

MODERNIZAÇÃO DA INSTRUMENTAÇÃO E CONTROLE DAS CALDEIRAS 8 E 9 NA CENTRAL TERMOELÉTRICA 1 DA CSN

MODERNIZATION OF INSTRUMENTATION AND CONTROL OF THE BOILER 8 AND 9 IN CSN THERMOELECTRIC PLANT 1

DOI

10.5151/2594-3626-25586

Downloads

Baixar Artigo 1183 Downloads

Resumo

A central termoelétrica número 1 (CTE#1) da Companhia Siderúrgica Nacional possui duas caldeiras em operação denominadas 8 e 9 com capacidade total de produção de vapor de 200 Toneladas por hora. Estas caldeiras fornecem vapor para os turbo geradores e turbo sopradores da CTE#1, além de vapor de processo para a Usina Presidente Vargas (UPV). As caldeiras entraram em operação em 1982/83 e seus sistemas de controle e instrumentação eram totalmente pneumáticos. Ao longo do tempo foi surgindo dificuldades para reposição e manutenção dos componentes pneumáticos, motivo pelo qual se iniciaram os estudos para substituição deste sistema. Em 2009 teve início um projeto para substituição do controle pneumático por um controle microprocessado feito por PLC redundante trabalhando com um supervisório scada e para substituição das malhas de instrumentação pneumática por instrumentação em rede fieldbus. A substituição completa dos componentes pneumáticos foi concluída em 2012. O novo sistema implantado trouxe diversas melhorias na performance, confiabilidade, segurança operacional e ergonomia. Este trabalho apresenta as causas que motivaram o projeto em questão, a metodologia utilizada para a sua implantação e os resultados alcançados com a aplicação de tecnologia moderna para controle e instrumentação de caldeiras.

 

The thermoelectric plant number 1 (CTE#1) of the National Steel Company has two boilers in operation called 8 and 9 with total production capacity of 200 tons of steam per hour. These boilers provide steam for the turbo generators and turbo blowers of CTE #1, besides process steam to the Vargas President Steelworks. The boilers were put into operation in 1982/83 and its control systems and instrumentation were completely pneumatic. Over time was appearing difficulties for replacement and maintenance of pneumatic components, reason whereby the studies began to replace this system. In 2009 began a project to replace the pneumatic control by a microprocessor control done by redundant PLC working with a supervisory SCADA and to replacement of pneumatic instrumentation loops for instrumentation with fieldbus network. The complete replacement of pneumatic components was completed in 2012. The new system deployed has brought many improvements in performance, reliability, operational safety and ergonomics. This work presents the causes that motivated the project in question, the methodology used for its implementation and the results achieved with the application of modern technology for boilers control and instrumentation.

Palavras-chave

Caldeiras; Instrumentação; Controle; Pneumático

Boiler; Instrumentation; Control; Pneumatic

Como citar

Milson de Andrade Júnior; Junior Teixeira Camargo; André Luis de Oliveira; André Galdino Pontes Ferreira. MODERNIZAÇÃO DA INSTRUMENTAÇÃO E CONTROLE DAS CALDEIRAS 8 E 9 NA CENTRAL TERMOELÉTRICA 1 DA CSN , p. 4403-4417. In: 35° Seminário de Balanços Energéticos Globais e Utilidades e 29° Encontro de Produtores e Consumidores de Gases Industriais, São Paulo - Brasil, 2014.
ISSN: 2594-3626 , DOI 10.5151/2594-3626-25586