Título

MODERNIZAÇÃO DO SISTEMA DE SOPRO DA ARCELORMITTAL PECÉM EM 198 HORAS

MODERNIZATION OF THE BLOWING SYSTEM AT AMT PECÉM IN 198 HOURS

DOI

10.5151/2594-5327-40403

Downloads

Baixar Artigo 9 Downloads

Resumo

O Sistema do regenerador do Alto Forno da ArcelorMittal Pecém era composto por 03 regeneradores de combustão interna de topo, uma linha de ar quente (HBM – Hot Blast Main) interligando os regeneradores ao Alto Forno, e equipamentos tais como ventaneiras e sistema de recuperação de calor para aumentar a temperatura do BFG (Blast Furnace Gás – gás de alto-forno) e do ar de combustão. Contava com 3 Regeneradores, HBS#1 a HBS#3, que operavam da seguinte forma: um (01) regenerador em operação, soprando e dois (02) regeneradores em aquecimento. É necessário que sempre haja 02 regeneradores em aquecimento, de forma que não haja perda de produção. Portanto, para que possam ser feitos reparos a frio nos regeneradores #1 e #3, houve a necessidade de implantar o regenerador #4. Em paralelo a construção do regenerador #4, a equipe de engenharia da ArcelorMittal Pecém em conjunto com a Reframax elaborou um estudo, tendo por objetivo a estabilização da linha de ar quente, substituição e estabilização dos ramais dos HBS#1, HBS#2 e HBS#3, juntamente com a interligação do HBS#4, com a concepção de projeto de atirantamento dos ramais da linha de ar quente e reparo da junta “T”, em 198 horas, tempo desafiador, não atingido a nível internacional.

 

The ArcelorMittal Pecém Blast Furnace St oves System consisted of 03 state-of-the-art internal combustion St oves, a hot air line Blast Main connecting the St oves to the Blast Furnace, and equipment such as tuyeres and a heat recovery system to increase BFG (Blast Furnace Gas) and combustion air temperature. It had 3 St oves, HBS#1 to HBS#3, which operated as follows: one (01) St oves in operation, blowing and two (02) St oves in heating. It is necessary that there are always 02 St oves heating, so that there is no loss of production. Therefore, in order to carry out cold repairs on St oves #1 and #3, St oves #4 had to be installed. In parallel with the construction of St oves #4, the ArcelorMittal Pecém engineering team, together with Reframax, prepared a study, with the objective of stabilizing the hot blast main, replacing and stabilizing the branches of HBS#1, HBS#2 and HBS#3, together with the interconnection of HBS#4, with the design of the met allic tie rodding project for the hot blast main branches and repair of the “T” joint, in 198 hours, a challenging time, not know n in ot her internatuonal references.

Palavras-chave

Alto Forno; Regeneradores; Sistema de Sopro; Engenharia de Manutenção

Blast Furnace; Regenerators; Blowing System; Maintenance Engineering