UTILIZANDO-SE DE MOINHO LABORATORIAL, FOI AVALIADO A UTILIZAçãO DE DIFERENTES TOPSIZE PARA A CARGA DE BOLAS NA ETAPA DE REMOAGEM DA SAMARCO MINERAçãO – E SEUS IMPACTOS NOS DEMAIS PARâMETROS DE PROCESSO. OS DIâMETROS AVALIADOS FORAM DE 35; 30; 25 E 20MM (SENDO 15MM O DIâMETRO DE EXPURGO CONSIDERADO), MENSURANDO POSSíVEIS VARIAçõES NO CONSUMO ENERGéTICO, CONSUMO DE BOLAS, GERAçãO DE SUPERFíCIE ESPECíFICA, ETC. EM UMA VISãO “MíOPE” E LEVANDO-SE EM CONSIDERAçãO APENAS AS OPERAçõES UNITáRIAS DE GERMANO, ALTERAçõES DO TOPSIZE DA CARGA PODERIA NãO SER VIáVEL ECONOMICAMENTE. PORéM, NUMA VISãO SISTêMICA E LEVANDO-SE TAMBéM EM CONSIDERAçãO AS OPERAçõES UNITáRIAS DE PONTA UBU, ALTERAçõES DO TOPSIZE DA CARGA PODERIAM TRAZER BENEFíCIOS GLOBAIS à SEREM CONSIDERADOS. SE TAIS RESULTADOS FOREM REPLICADOS EM ESCALA INDUSTRIAL, HAVERIA GANHOS DA ORDEM DE R$ 1,0-8,0 M/A (à DEPENDER DA REDUçãO DA SUPERFíCIE ESPECíFICA OBTIDA NO PRODUTO REMOíDO) DEVIDO, PRINCIPALMENTE, A GANHOS DE PRODUTIVIDADE NA ETAPA DE FILTRAGEM E REDUçãO DE CUSTOS NA ETAPA DE ENDURECIMENTO.
USING A LABORATORY MILL, WAS EVALUATED THE APPLICATION OF DIFFERENT TOPSIZES FOR THE BALL CHARGE IN THE REGRINDING STAGE AT SAMARCO MINERAçãO – AND THEIR IMPACTS ON THE OTHER PROCESS PARAMETERS. THE DIAMETERS EVALUATED WERE 35; 30; 25 AND 20MM (BEING 15MM THE PURGE DIAMETER CONSIDERED, ACCORDING TO INDUSTRIAL SCALE), MEASURING POSSIBLE VARIATIONS IN THE ENERGY CONSUMPTIONS, BALL CONSUMPTIONS, GENERATION OF SPECIFIC SURFACE, ETC. IN A SHORT VIEW AND TAKING INTO CONSIDERATION ONLY THE GERMANO’S UNIT OPERATIONS, CHANGES IN THE CHARGE BALL TOPSIZE COULD NOT BE ECONOMICALLY VIABLE. HOWEVER, IN A SYSTEMIC VIEW AND ALSO TAKING INTO ACCOUNT THE PONTA UBU’S UNIT OPERATIONS, CHANGES IN THE CHARGE BALL TOPSIZE COULD BRING IMPORTANTE GLOBAL BENEFITS TO BE CONSIDERED. IF SUCH RESULTS COULD REPLICATED ON THE INDUSTRIAL SCALE OF SAMARCO MINERAçãO, THERE WOULD BE GAINS OF THE ORDER OF R$ 1,0-8,0 M/A (DEPENDING ON THE REDUCTION OF SPECIFIC SURFACE IN THE REGROUND PRODUCT) DUE, MAINLY, TO GAINS IN THE PRODUCTIVITY OF THE FILTERING STEP AND REDUCTION IN THE OPERATIONAL COSTS OF THE BURNING/HARDENING STEP.
Keywords
Remoagem; Carga de bolas; Superfície específica; Visão sistêmica
Regrinding; Ball charge; Specific surface; Sistemic vision
How to refer
ULIANA, ALEXANDRO.
DEFINIÇÃO DO TOPSIZE DA CARGA DE BOLAS DA ETAPA DE REMOAGEM: UMA ABORDAGEM SISTÊMICA E LABORATORIAL
,
p. 757-771.
In: 23º Seminário de Mineração,
São Paulo, Brasil,
2024.
ISSN: 2594-357X
, DOI 10.5151/2594-357X-41565