Proceedings of ABM Annual Congress


ISSN 2594-5327

75° Congresso Anual da ABM vol. 75, num.75 (2022)


Title

IMPLANTAÇÃO DO PROCESSO DE CONFIABILIDADE OPERACIONAL NA PELOTIZAÇÃO DA VALE TUBARÃO: INDICADORES E RESULTADOS

IMPLEMENTATION OF THE OPERATIONAL RELIABILITY PROCESS AT VALE TUBARÃO PELLETIZING PLANT: INDICATORS AND RESULTS

DOI

10.5151/2594-5327-35001

Downloads

Abstract

A GESTÃO DE ATIVOS POR MEIO DA CONFIABILIDADE OPERACIONAL TEM SIDO TEMA PARA A OBTENÇÃO DE UM MELHOR VALOR DE ATIVOS PARA UMA INSTALAÇÃO. NO CASO DA PELOTIZAÇÃO, HÁ UMA CARÊNCIA EM DESCREVER O USO DE INDICADORES APLICADOS À CONFIABILIDADE OPERACIONAL. A PRESENTE CONTRIBUIÇÃO AVALIA, POR MEIO DE INDICADORES E RESULTADOS OBTIDOS, A IMPLANTAÇÃO DO PROCESSO DE CONFIABILIDADE OPERACIONAL NA PELOTIZAÇÃO DA VALE TUBARÃO. OS PRINCIPAIS INDICADORES FORAM: TEMPO DE PARADAS, TEMPO DE PERDAS E A QUANTIDADE DE EVENTOS RELACIONADOS COM A OPERAÇÃO. O TRABALHO VERIFICOU QUE, APÓS A IMPLEMENTAÇÃO DA CONFIABILIDADE, HOUVE UMA DIMINUIÇÃO DA DURAÇÃO DE PARADAS E PERDAS NAS USINAS A, C E E. OUTRAS USINAS FORAM IMPACTADAS OPERACIONALMENTE COM A OCORRÊNCIA DE EVENTOS ÚNICOS. A IMPLANTAÇÃO DA CONFIABILIDADE OPERACIONAL POSSIBILITOU O DEVIDO TRATAMENTO DE FALHAS CRÍTICAS E DE ROTINA, PRINCIPALMENTE REINCIDENTES, PROPICIANDO A DIMINUIÇÃO DA QUANTIDADE DE FALHAS. OS RISCOS DE PROCESSO FORAM TRATADOS E MINIMIZADOS A PARTIR DA ESTRUTURAÇÃO DA ROTINA DE CONFIABILIDADE.

 

ASSET MANAGEMENT THROUGH OPERATIONAL RELIABILITY HAS BEEN A THEME FOR ACHIEVING BETTER ASSET VALUE FOR A FACILITY. IN THE CASE OF PELLETIZING, THERE IS A LACK OF LITERATURE DESCRIBING THE USE OF OPERATIONAL RELIABILITY INDICATORS. THIS PAPER EVALUATES, THROUGH INDICATORS AND RESULTS OBTAINED, THE IMPLEMENTATION OF THE OPERATIONAL RELIABILITY PROCESS AT VALE TUBARãO PELLETIZING PLANT. THE MAIN INDICATORS WERE: DOWNTIME, LOSS TIME AND THE NUMBER OF EVENTS RELATED TO THE OPERATION. THE STUDY FOUND THAT, AFTER THE IMPLEMENTATION OF RELIABILITY, THERE WAS A DECREASE IN DOWNTIME AND LOSSES IN THE A, C AND E MILLS. OTHER PLANTS WERE OPERATIONALLY IMPACTED WITH THE OCCURRENCE OF SINGLE EVENTS. THE IMPLEMENTATION OF OPERATIONAL RELIABILITY ALLOWED FOR THE PROPER TREATMENT OF CRITICAL AND ROUTINE FAILURES, ESPECIALLY RECURRENT ONES, LEADING TO A REDUCTION IN THE NUMBER OF FAILURES. THE PROCESS RISKS WERE TREATED AND MINIMIZED FROM THE STRUCTURING OF THE RELIABILITY ROUTINE.

Keywords

Confiabilidade operacional; Perfil de perdas; Análises de falhas; Pelotização.

Operational reliability; Loss profile; Failure analysis; Pelletizing

How to refer

Rocha, Valéria Pontes de Jesus. IMPLANTAÇÃO DO PROCESSO DE CONFIABILIDADE OPERACIONAL NA PELOTIZAÇÃO DA VALE TUBARÃO: INDICADORES E RESULTADOS , p. 1461-1474. In: 75° Congresso Anual da ABM, São Paulo, 2022.
ISSN: 2594-5327 , DOI 10.5151/2594-5327-35001