Abstract

O objetivo do presente trabalho é mostrar a programação da parada e execução da reforma do forno de reaquecimento. Esta parada se espelhou nas experiências de Novembro de 1996 e programou-se a troca completa da soleira, troca completa do teto, troca das paredes laterais da região de pré-aquecimento, troca da parede frontal de enfornamento, paredes frontais dos queimadores da zona 1, zona 2 e encharque. Em termos de programação esta parada contratualmente foi prevista para ser executada em 16 dias, porém, o tempo objetivado foi de 15 dias. Buscando o melhor para o forno do ponto de vista técnico optou-se em manter os bons resultados anteriores e desta forma a soleira, paredes laterais e parede frontal de enfornamento ficaram a cargo do fornecimento da Magnesita S/A, o teto e paredes frontais de queimadores ficaram a cargo da Safran Linco Ltda. A mão de obra para execução destes serviços ficou sob responsabilidade da Reframax, o resfriamento/secagem sob responsabilidade da Termojet.

 

The objective of is to work is this shown the planning on stopping and executting the reheating furnace rebuild. Such rebuild was modelled on the November/96 experience and the complete change of the hearth, the complete change of the roof, the change of the pre heating side walls, the change of the charging partition wall, the partition wall of the gás burner in zones one and two and the soaking zone, were programmed. As far as programming, this stop was expected to be executed within sixteen days, although the executing time covered fifteen days. Viewing the best to the furnace in techmical terms, we opted to keep the good results as before. For that, the side walls and the charging partition walls were under Magnesita’s responsibility, the roof and the partition walls of the gás burner were under Safran Linco’s, the labour in executing the job was under Reframax’s responsibility. Cooling and drying were done by Termojet.

Keywords

parada, Reforma, Forno

Stopping, Rebuilding, Furnace

How to refer

Magalhães, Fernando Antonio Bartolomeu; Amanuma, Toshio; Silva, Nevadir Rodrigues da; Martins, Widison José. REFORMA DO FORNO DE REAQUECIMENTO DE TARUGOS NA LAMINAÇÃO DA BELGO JUIZ DE FORA , p. 830-842. In: 41º Seminário de Laminação, Processos e Produtos Laminados Revestidos, Joinville - SC, 2004.