PLANEJAMENTO E EXECUÇÃO DE PARADA PARA A 2ª TROCA DE STAVES NO ALTO-FORNO 3 DA USIMINAS

PLANNING AND EXECUTION OF USIMINAS’ BLAST FURNACE 3 BLOW DOWN FOR THE SECOND STAVES EXCHANGE

DOI

10.5151/2594-357X-33809

Downloads

Baixar Artigo 389 Downloads

Resumo

O Alto-Forno 3 da Usiminas iniciou sua atual campanha em 1999. Projetada para durar 15 anos de operação, previa-se uma produção de 41 Mt de gusa. A partir de 2008, iniciaram as avarias mais significativas no sistema de refrigeração, possibilitando a entrada de água e os consequentes distúrbios operacionais. Buscando estender a atual campanha até 2021, a Usiminas realizou, dentre outras atividades de preservação, duas trocas de staves, em 2015 e 2018. Neste trabalho, são apresentados o planejamento e os principais procedimentos relacionados à parada operacional do alto-forno para a segunda troca de staves, com foco nas atividades operacionais que permitiram a redução do nível da carga até 25,1 metros em relação ao stock line. Destacam-se os cuidados e o êxito no abaixamento de carga até o nível das ventaneiras e a metodologia de troca de staves adotada. Por fim, a previsão de extensão da campanha em 7 anos, possibilitará atingir uma produção acumulada de 53,5 Mt, superando em 12,5 Mt o valor projetado

 

Usiminas’ Blast Furnace 3 started its current campaign in 1999. Designed to last 15 years of operation, it was expected to produce 41Mt of pig iron. In 2008, wear in the refrigeration system began significantly, allowing water leaks and consequent operational disturbances. In order to extend the current campaign to 2021, Usiminas has carried out, among other preservation activities, two staves exchanges, in 2015 and 2018. In this paper, the planning and main procedures related to the blowdown of the furnace for the second stave exchange is approached. It focuses on the operational activities that allowed the reduction of the burden level down to 25.1 meters below the stock line. The success of lowering burden to the tuyeres level and the methodology adopted is outstanding. Finally, the 7 year extension in the campaign will allow a production of 53.5Mthm, surpassing by 12.5Mthm the projected value

Palavras-chave

Alto-Forno; Staves

Blast furnace; Staves

Como citar

Generoso, Lucas Gonçalves; Santos, Gustavo Serrano dos; Rocha, Larissa Rodrigues de Carvalho; Manso, Gustavo Alexandre da Costa; Fernandes, Mauro Vivaldino. PLANEJAMENTO E EXECUÇÃO DE PARADA PARA A 2ª TROCA DE STAVES NO ALTO-FORNO 3 DA USIMINAS , p. 337-347. In: 49° Seminário de Redução de Minérios e Matérias-primas, São Paulo, 2019.